Rockets rally for first league win Lady Broncos rise to 10-6 with win at Wilmington Broncos begin quest for SBAAC American Div. title Lady G-Men looking to bounce back from recent losses SHAC golf season in the books Lady Rockets top Whiteoak Fair Royalty chosen for 2016 Troop Box Ministry still going strong after 15 years Three sentenced in Common Pleas Alex K Miller Denvil Burchell Maneva H Teague Vincent A Cluxton Stanley J Brannock Robert L Dyer Mary L Phillips Broncos gallop to 9-0-1 with win over G-Men Tight battle continues for SBAAC American Division volleyball title Jays rally for win over Rockets Week 4 football roundup Sininger is SBAAC Nat’l Division Golfer of Year Lady Rockets top CCD, fall to CNE Janet R Reveal Paul D Hines Gas skimmers stealing identities Democrats meet in G’town Humane Society horses now up for adoption New ‘B-Fit Program’ at this year’s fair Drug Task Force marijuana eradication Cheryl L Sams Aaron S Cartwright Tommie E Stout Rockets soar past the Warriors, 5-0 G-Men place runner-up in Vern Hawkins XC Invite Lady Warriors cruise to victory over Fayetteville Broncos remain unbeaten at 6-0-1 Lady G-Men win at Ripley Week 3 football roundup Broncos lead after round two of SBAAC American Division play Ohana Music Festival a huge success Man charged with 292 counts of child porn possession G’Town Council resolves zoning issues, to hold public meeting on medical marijuana Chase pleads guilty to obscenity charges Georgetown Nativity Scene to be on display, much longer this year Georgetown Police Chief Rob Freeland, updates council on village happenings Jay R Crawford Kenneth James Verne Wisby, Sr Kenneth J Barber Olivette F Corbett David E Kelsey, Sr Betty A Stegbauer Virginia McConnaughey Chantal C Cook Chase pleads guilty to obscenity charges Brown County jobless rate at 16 year low UC to eliminate smoking on campus Marjorie M Hardy James A Housh SWRMC Home Health business is sold Man charged after a fight results in death Six sentenced in Common Pleas Bevens running for Ohio State Board of Education Donna Frost to perform in Georgetown Sept. 8 2016 HIKE 4 HOPE 3-Mile Walk Run set for Sept. 11 James Adams, Sr Ashley D Ring, Sr Gladys Warner 2016 Prep Football Preview Anna M Huber Patricia L Slagle Colleen S Hannah Helen B Hensley Nick Owens to run for state board of education Ten indicted by Brown County Grand Jury Troop Box Ministries alive and well, continues to send gift boxes to troops after 16 years Veteran’s Home Golf Tournament planned Four sentenced in common pleas Susan G Simpson Mary P Walsh Jerald R Hauke Charles Rodenberg Shelia D Fist Shirley M Josche John T Denier Raymond L Knell Dorothy E Holton Jayce CJ Bradford Georgetown asked to pay for full time drug officer 2016 Ohio Valley Antique Machinery Show ODOT opens new maintenance building Glenn O Stroop Jr Lloyd M Malott John J Ward Mae F Miller Robert E Nash Jay D Cutrell Cyclist’s death under investigation Wenstrup visits Mt. Orab Two planes crash in Brown County

Aicholtz Road construction planned

By Megan Alley

Construction on the Aicholtz Road connector project will begin in a couple of weeks.
The project, with an estimated construction cost of $6.5 million, will reduce congestion on state Route 32 by providing another route for drivers to travel from the Eastgate area to Mt. Carmel Tobasco Road, according to officials.
Aicholtz Road was disconnected in the early 1970s when Interstate 275 was built, said Craig Stephenson, Clermont County chief deputy county engineer, earlier this year.
The road, which currently “zigs and zags” on the west side, will be straightened and widened from two lanes to three, according to Pat Manger, Clermont County engineer.
A sidewalk that will reach Ivy Pointe will be added to the south side of the road, according to Stephenson.
About 30 homes are located along the Aicholtz Road corridor, Manger estimated.
The east side of the project, also referred to as “phase one,” will be constructed first. This area is comprised of Aicholtz Road from Eastgate to the new Interstate 275 underpass.
“What we’re trying to do is get the east side done first, so that way, when they start working on the west side, the people kind of have a way out the back door, so to speak,” Manger explained.
Construction on phase one is expected to wrap this fall; the segment of the road will be open throughout the construction of phase two, which is expected to start next spring.
“They want to get the east end rehabbed and widened, so that when they start in and try to realign the west end, it will allow people to escape, and go to and from the east, so they aren’t forced to go through the construction traffic,” Manger said. “Now, there are probably some people that live on the west side that are still going to head out towards Mt. Carmel Tobasco.”
He added, “The idea is to create a link back to the east to give people options, so if you live on the west side, you’re still going to go towards Mt. Carmel Tobasco, but if you live towards the east, now you can go under the bridge

and get on out that way.”
Final construction of both phases is expected to be completed by fall 2017.